year operator address production cumulative opening depth seam thickness method days emp
1879 Thomas Balby Chesterfield 150 150 drift #5
1882 Rudolph & Beilby 626 drift #5 6 12 mo 1
1883 1,200 1,826 drift 6 12 2
1884 Beilby & Co. 2,000 drift 6 210 2-4
1885 2,200 4,200 drift #6 6 RP 200 2-4
1886 Beilby & Rudolph 2,000 2,000 drift #6 6 RP 218 2-4
1887 Beilby & Co. 2,000 shaft 60 #6 6 RP 220 3
1888 2,212 280 5
1889 2,420
1890 2,512
1891 0
1892 0
1893 0
1894 0 9,144
1895 August Bode 500 slope #5 5 RP
1896 0
1897 0 500
1898 W. H. A. Bodi 90 drift 5.5
1899 1,440 drift 50 5.5
1900 1,418 50 5.5 RP
1901 1,322
1902 1,220
1903 1,050 slope 50 pocket 5.5 RP
1904 825 shaft 30 pocket RP
1905 1,600 slope 30 pocket RP
1906 0
1907 0
1908 0 8,965
1909 W. H. H. Bode 250 250 shaft 40 #5 4.5 RP
27,035