year | DMM | operator | address | production | cumulative | opening | depth | seam | thickness | method | days | emp |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1901 | Vinegar Hill Coal Co. | New Athens | 9,177 | 9,177 | 125 | 16 | ||||||
1902 | Kolb Coal Co., Vinegar Hill | Mascoutah | 48,782 | 204 | 36 | |||||||
1903 | Mascoutah | 88,796 | 210 | 62 | ||||||||
1904 | 80,590 | 190 | 65 | |||||||||
1905 | Mascoutah | 55,751 | 150 | 70 | ||||||||
1906 | New Athens | 33,309 | shaft | 80 | #6 | 7 | 111 | 35 | ||||
1907 | Mascoutah | 39,227 | shaft | 180 | #6 | 7 | 150 | 29 | ||||
1908 | Mascoutah | 59,270 | shaft | 80 | #6 | 7 | RP | 187 | 43 | |||
1909 | Mascoutah | 27,800 | shaft | 180 | #6 | 7 | RP | 120 | 29 | |||
1910 | New Athens | 33,050 | 160 | 43 | ||||||||
1911 | New Athens | 21,340 | 136 | 35 | ||||||||
1912 | New Athens | 13,499 | 77 | 30 | ||||||||
1913 | New Athens | 561 | 5 | 14 | ||||||||
1914 | New Athens | 16,582 | 58 | 39 | ||||||||
1915 | 0 | |||||||||||
1916 | 0 | |||||||||||
1917 | New Athens | 24,262 | shaft | #6 | 6 | RP | 122 | 53 | ||||
1918 | New Athens | 52,859 | shaft | 90 | #6 | 7 | RP | 176 | 65 | |||
1919 | New Athens | 45,821 | shaft | 90 | #6 | 7 | RP | 136 | 57 | |||
1920 | New Athens | 41,128 | shaft | 90 | #6 | 7 | RP | 125 | 60 | |||
1921 | New Athens | 33,161 | shaft | 90 | #6 | 7 | RP | 91 | 60 | |||
1922 | 0 | 715,788 | ||||||||||
1923 | Kolb Coal Co., No. 4 | New Athens | 21,815 | |||||||||
1924 | 0 | |||||||||||
1925 | 0 | |||||||||||
1925b | 0 | |||||||||||
1926 | 0 | |||||||||||
1927 | 0 | |||||||||||
1928 | 0 | 21,815 | ||||||||||
1929 | Vinegar Hill Coal Co. | Lenzburg | 21,715 | shaft | 90 | #6 | 6 | RP | 64 | 54 | ||
1930 | Lenzburg | 58,047 | shaft | 90 | #6 | 6.67 | RP | 134 | 58 | |||
1931 | Lenzburg | 84,062 | shaft | 90 | #6 | 6.67 | RP | 165 | 69 | |||
1932 | Lenzburg | 79,897 | shaft | 90 | #6 | 6.67 | RP | 172 | 61 | |||
1933 | Lenzburg | 92,282 | shaft | 90 | #6 | 6.67 | RP | 154 | 62 | |||
1934 | Lenzburg | 78,974 | shaft | 90 | #6 | 6.5 | RP | 145 | 65 | |||
1935 | Lenzburg | 74,240 | shaft | 90 | #6 | 6.5 | RP | 143 | 67 | |||
1936 | Lenzburg | 83,433 | shaft | 90 | #6 | 6.83 | RP | 148 | 75 | |||
1937 | S-19 | Lenzburg | 77,654 | shaft | 95 | #6 | 6.5 | RP | 140 | 75 | ||
1938 | S-19 | Lenzburg | 30,601 | shaft | 95 | #6 | 6.5 | RP | 64 | 58 | ||
1939 | S-19 | Lenzburg | 57,335 | shaft | 95 | #6 | 6.5 | RP | 123 | 30 | ||
1940 | S-19 | Lenzburg | 45,086 | shaft | 95 | #6 | 6.5 | RP | 91 | 66 | ||
1941 | S-19 | Lenzburg | 53,471 | shaft | 96 | #6 | 6.5 | RP | ||||
1942 | S-19 | Lenzburg | 74,256 | shaft | 96 | #6 | 6.5 | RP | 182 | 61 | ||
1943 | S-19 | Lenzburg | 93,486 | shaft | 96 | #6 | 6.5 | RP | 202 | 67 | ||
1944 | S-19 | Lenzburg | 56,784 | shaft | 96 | #6 | 6.5 | RP | 161 | 45 | ||
1945 | S-19 | Lenzburg | 19,886 | shaft | 96 | #6 | 6.5 | RP | 97 | 30 | ||
1946 | S-19 | Lenzburg | 3,813 | 1,085,022 | shaft | 96 | #6 | 6.5 | RP | |||
1946 | S-19 | Okaw Coal Co., Vinegar Hill | Lenzburg | 20,055 | shaft | 96 | #6 | 6.5 | RP | 133 | 41 | |
1947 | S-19 | Lenzburg | 57,858 | shaft | 96 | #6 | 6.5 | RP | 193 | 54 | ||
1948 | S-19 | Lenzburg | 39,662 | 117,575 | shaft | 90 | #6 | 6 | RP | 118 | 54 | |
1,949,377 |